Guestroom vinyl wall covering is complete on the second and third floors - roughly 3 weeks ahead of schedule. The guest bath vinyl is anticipated to arrive mid January and to be completed in 2 weeks. Vanities and granite will start immediately after installation of the VWC on a floor by floor basis. The tub surrounds are complete on the third and fourth floors. Overall, the guestroom and guest bathrooms are running 3-4 weeks ahead of schedule.
Water heaters and mechanical units have arrived and been arranged in the mechanical rooms.
The Hampton Inn sign on the building is now installed.
Major purchases of FF&E and OS&E will commence in January