Construction Update

Work is progressing smoothly with exterior stone veneer continuing and anticipated to be completed before the holidays. All exterior façade work will be completed at that time. Only minor site work and landscaping will remain in the spring.

The interior of the project is running smoothly as well, with painting well underway in the guest room floors. Drywall is nearly complete with only the first floor remaining. The drywall is paint ready on all floors. The interior of the project is ahead of schedule. The contractor is anticipated to be complete by the end of April for our mid to late May opening.