Wednesday, February 25, 2009

Overall Update

The project is now moving toward completion and final installations of materials are underway. Finishes are complete in guest rooms and guest baths and carpet installation has commenced. Hotel Operations has begun the procurement of operator material and is preparing to move into the hotel on April 1, 2009. We anticipate being open by early May 2009.

The procurement of all furniture fixtures and equipment is nearly complete, with a majority of the goods currently in storage awaiting installation. Early installation of furniture, particularly the guest room headboard hardware, will commence this month to further the efficiency of the schedule.

On the operations side, all department heads have been hired with the exception of the Chief Engineer. We have a final candidate here and expect to make a decision within the next week or so.

New pictures should be added the week of March 2nd.